Главная
страница
Сведения об авторах
TREATMENT OF LANDFILL LEACHATE BY INTEGRATED HORIZONTAL-FLOWCONSTRUCTED WETLANDS
Lei Yang, Yi-Lin Chen, National Sun Yat-sen University, Kaohsiung, Taiwan
Landfill leachate treatment can be
expensive and energy-intensive achieved in advanced wastewater
treatment plants. One possible method to reduce cost and energy
requirements is to treat the leachate on-site using constructed
wetlands. In this study, we investigated the feasibility of
treating the leachate from a ten-year old landfill site, with
high ammonia levels and low BOD/COD ratio, by pilot-scale
constructed wetlands. An integrated horizontal-flow constructed
wetland system fed by original landfill leachate was used in this
study. The integrated constructed wetland system contained two
basins connected in series: one installed as free water surface
(FWS) constructed wetland, and the other as subsurface flow (SSF)
one, both of which were in the same size of 2 m(L)x1 m(W)x1 m(H).
The FWS system was planted with reeds (Phragmites australis),
while the SSF system was planted with evergreen (Dracaena
sanderiana cv.). After one-year operation, the experimental
results showed that this constructed wetland system performed
better in the condition of hydraulic retention time (HRT)
controlled at 5 days than that at 10 days for both nitrogen
removal and BOD, while almost half of COD was removed in both
controlled HRT conditions in the experiment. According to the
analytical results, the removal efficiencies of total nitrogen
(TN) and ammonia (NH3-N) were measured equal to 62%
and 79%, respectively in HRT of 5 days, while the values were
measured equal to 52% and 74%, respectively for HRT controlled in
10 days. For BOD removal efficiencies, the condition of 5-day HRT
presented 67%, while it was measured equal to 28% for HRT
controlled in 10 days. Meanwhile, the removal efficiency of COD
was found equal to the same value of 46% in both HRT conditions
controlled in this study. However, we found that both total
phosphorous (TP) and phosphate (PO4-3)
exhibited higher removal efficiencies in the test run of HRT
controlled in 10 days than that in 5 days, which was because PO4-3
was removed mainly by chemical adsorption onto the medium
surface used in constructed wetland systems. The media might have
been saturated in the second stage of test run with HRT
controlled in 5 days. The reason why the removal efficiencies of
TN were lower than NH3-N was believed due to less
active for denitrifying bacteria in systems. It was believed that
lack of organic carbon source in the secondarily treated leachate
would result in insignificant denitrification to make nitrate
build-up in the system. There are two conditions required for
denitrification: one is anoxic environment, and the other is
sufficient organic carbon sources. In constructed weland systems,
the medium surface could provide an anoxic sites to achieve
denitrification occurring. Hence, deficient of organic carbon
source was the only reason to depress denitrification in wetland
system to treat aged landfill leachate. Therefore, we tried to
add extra organic carbon sources (fructose and molasses) into the
wetland systems to verify this hypothesis in the final stage of
test run. The experimental results showed that the higher the
amounts of BOD were added into the wetland system, the higher the
amounts of TN were found removed. These experimental results
surely confirmed that adding BOD into a wetland system could help
to achieve complete denitrification.
Lei Yang, prof., Department of Marine Environment and Engineering, National Sun Yat-sen University, 70 Lien-Hai Road, Kaohsiung 804, Taiwan. Tel. (7) 525-20-00 (ext 50-68), fax (7) 525-50-68. E-mail
© Независимое агентство экологической информации
Последние изменения внесены 10.07.07